FANG Pei. Water Control and Effect Evaluation in Annular Space of Freezing Shaft Hole[J]. Safety in Coal Mines, 2015, 46(12): 200-202.
Citation: FANG Pei. Water Control and Effect Evaluation in Annular Space of Freezing Shaft Hole[J]. Safety in Coal Mines, 2015, 46(12): 200-202.

Water Control and Effect Evaluation in Annular Space of Freezing Shaft Hole

More Information
  • Published Date: December 19, 2015
  • If the shaft construction adopts full deep freezing method after the frozen wall thawing, the annular space between inside and outside the freezing hole easily becomes water channel, which is a serious threaten to mine safety. The west air shaft in Qianyingzi Coal Mine is constructed by full freezing method. When the shaft constructs to the well bottom sump, the upper local aquifer thaws out of the water, the total yield reaches to 25 m3/h. As large amounts of water rock runs off, one side of shaft bottom upwards along the freezing hole caving forms a big hole. Through the research analysis, point-to-point lacerate grouting and deep hole grouting by subsection were used, which effectively governed the annulus water in freezing hole. The water channel is also plugged obviously and the surrounding rock is reinforced, so shaft total yield dropped below 0.5 m3/h.
  • [1]
    隋旺华,董青红,蔡光桃,等.采掘溃砂机理与预防[M].北京:地质出版社,2008.
    [2]
    王心义,王世东,刘白宙,等.矿井煤层底板含水层注浆改造技术[J].矿业研究与开发,2005,25(6):86.
    [3]
    李燕,孙亚军,徐智敏,等 .影响矿井安全的多含水层矿井涌水构成分析[J]. 采矿与安全工程学报,2010,27(3):433-437.
    [4]
    王永红,沈文.中国煤矿水害预防及治理[M].北京:煤炭工业出版社,1997.
    [5]
    丛山.矿山帷幕注浆堵水工程设计与施工[M].北京:地质出版社,2011.
    [6]
    范天吉.煤矿防治水综合技术手册[M].长春:吉林音像出版社,2003.
  • Related Articles

    [1]QIU Nianguang, LI Songying, YAN Guocai, YAO Xiaoshuai, ZHANG Wanpeng, JIN Mingfang, ZHAO Hongli. Transient electromagnetic response characteristics and application of roof water channel[J]. Safety in Coal Mines, 2024, 55(7): 179-187. DOI: 10.13347/j.cnki.mkaq.20230860
    [2]LI Zhi, ZHENG Shitian, WANG Yuhang. Technology and application of integrated treatment of water source and channel for floor borehole water inrush in Zhuzhuang Coal Mine[J]. Safety in Coal Mines, 2023, 54(6): 193-198.
    [3]LIANG Zhipeng, CHENG Zihou, YUAN Shuai. Application of Cutting Hole Grouting Technology in Water Prevention and Control of Western Fully Frozen Vertical Shaft[J]. Safety in Coal Mines, 2018, 49(4): 128-131.
    [4]LI Chong, WANG Junxian. Control Techniques for Ordovician Limestone Karst Water Disaster with High-pressure in Deep Mining[J]. Safety in Coal Mines, 2018, 49(2): 71-72,76.
    [5]LIANG Qinghua. Water Disaster Exploration and Control in Coal Mines of South China[J]. Safety in Coal Mines, 2017, 48(2): 171-173.
    [6]LI Chong. Control Techniques for Ordovician Limestone Karst Water Disaster in Deep Mines[J]. Safety in Coal Mines, 2016, 47(5): 101-103.
    [7]HUANG Chongxiao, ZHANG Yaohui. Water Disaster Treatment Technology of Serious Water-bearing Layer Based on Floor River-closure Theory[J]. Safety in Coal Mines, 2015, 46(9): 90-92,95.
    [8]ZHAN Youming. Reasonable Location of Annular Water-intercepting Roadway Based on Shaft Water Disaster Control[J]. Safety in Coal Mines, 2015, 46(2): 32-35,39.
    [9]ZHANG Ping-qing. Practice of Limestone Water Regional Governance in Pingdingshan Mining Area[J]. Safety in Coal Mines, 2013, 44(10): 169-171,172.
    [10]SHAO Hong-qi. Sealing Deep Freezing Bedrock Shaft Frozen Hole Bursting Water Technology with Water Diversion Grouting[J]. Safety in Coal Mines, 2013, 44(1): 74-76,79.