WANG Canhua, LIANG Lixun, ZHUO Jun, FAN Jianyong, CHENG Changyong, HU Yongsheng. Safety Rapid Installation Technology for Steep Inclined Fully Mechanized Working Face[J]. Safety in Coal Mines, 2015, 46(2): 99-102.
    Citation: WANG Canhua, LIANG Lixun, ZHUO Jun, FAN Jianyong, CHENG Changyong, HU Yongsheng. Safety Rapid Installation Technology for Steep Inclined Fully Mechanized Working Face[J]. Safety in Coal Mines, 2015, 46(2): 99-102.

    Safety Rapid Installation Technology for Steep Inclined Fully Mechanized Working Face

    • In order to solve the problem of large inclined angle seam, slow lifting reprint and flat car transport installation process, big labor intensity, unsafe operation caused safety accidents in steep inclined coal seam fully mechanized equipment installation, taking green water 3114 inclined fully mechanized face equipment installation as the research object, we propose the installation process of pouring transport platform through the horizontal self sliding installation technology of decentralization, analyze its technical characteristics, and research full mechanized mining equipment installation process and matching device. The industrial test results show that the transverse self sliding safety quick installation process solves the problem of installation steering, steep inclined fully mechanized mining face equipment dumping problem, realizes the rapid installation and alleviates the pressure of mine production follow.
    • loading

    Catalog

      Turn off MathJax
      Article Contents

      /

      DownLoad:  Full-Size Img  PowerPoint
      Return
      Return