Construction Technology of Grouting Curtain for Overburden Burnt Rock in Waiting Mining Face
-
摘要: 为了研究张家峁煤矿5-2煤待采工作面上覆4-2煤烧变岩帷幕注浆技术,分析了烧变岩水文地质特征和帷幕工程实施原因,论述了帷幕工程设计,从钻孔施工顺序、浆液流向干扰、注浆方法优化等方面研究了注浆帷幕的建造方法。工程实践表明:待采工作面上覆烧变岩注浆帷幕建造应按照先内排后外排的顺序,采用井上下双位双向综合引流方法,帷幕线上不同烧变岩断面应进行分区注浆。Abstract: To study the burnt rock curtain grouting technology of overburden 4-2 coal in Zhangjiaomao Coal Mine, the hydro-geological characteristics of burnt rock and the causes of curtain engineering are analyzed, and the design of curtain engineering is discussed, and the sequence of drilling construction is discussed. The construction method of grouting curtain is studied in the aspects of grouting flow interference, grouting method optimization and so on. The engineering practice shows that the grouting curtain construction of overburden burnt rock on the working face should be based on the sequence of the first internal discharge and then the outer drainage, and the method of double position bidirectional comprehensive drainage grouting should be adopted, and the different burnt rock sections on the curtain line should be partitioned grouting.
-
-
[1] 张渝,胡社荣,彭纪超,等.中国北方煤层自燃产物分类及宏观模型[J].煤炭学报,2016,41(7):1798. [2] 范立民,仵拨云,向茂西,等.我国西部保水采煤区受保护烧变岩含水层研究[J].煤炭科学技术,2016,44(8):1-6. [3] 韩德馨,孙俊民.中国煤的燃烧变质作用与煤层自燃特征[J].中国煤田地质,1998(4):15-16. [4] 侯恩科,童仁剑,冯洁,等.烧变岩富水特征与采动水量损失预计[J].煤炭学报,2017,42(1):175-182. [5] 杜中宁,党学亚,卢娜.陕北能源化工基地烧变岩的分布特征及水文地质意义[J].地质通报,2008(8):1168. [6] 王宏科,蒋泽泉,郭亮亮.张家峁煤矿15204工作面导水裂隙带高度探测[J].陕西煤炭,2015,34(2):31. [7] 苗彦平,马有宽,张建国.张家峁煤矿5-2煤顶板结构分析[J].陕西煤炭,2010,29(5):1-2. [8] 姬中奎.张家峁井田烧变岩与水库水力联系及帷幕截流技术研究[D].西安:西安科技大学,2018. [9] 邹光华,师皓宇,田多.基于泥砂介质的注浆渗流-渗透过程分析与力学机理[J].煤矿安全,2016,47(2):196-199. [10] 邵红旗.引流注浆封堵深基岩冻结井筒冻结孔涌水技术[J].煤矿安全,2013,44(1):74-76.
计量
- 文章访问数: 90
- HTML全文浏览量: 0
- PDF下载量: 0