    • 摘要: 针对大南湖一矿工作面回采过程中存在的异常涌水问题,以大南湖一矿1303工作面为研究对象,通过相似模拟试验对工作面回采过程中顶板覆岩破坏演化过程进行研究,揭示纵向主干涌水裂隙的演化特征及工作面异常涌水规律,得出覆岩纵向主干涌水裂隙的恶性扩张是发生异常涌水的主要原因,根据研究成果提出相应的控制对策,为大南湖一矿1303工作面异常涌水防治提供保障。

       

      Abstract: Aiming at the problem of abnormal water gushing in the mining process of Dananhu No.1 mine, taking 1303 working face of Dananhu No.1 mine as the research object, the failure evolution process of roof overburden in the mining process of working face is studied by means of similar simulation test to reveal the evolution characteristics of longitudinal trunk water-inrush crack and abnormal water-inrush law of working face. According to the research results, the corresponding control countermeasures are proposed to guarantee the prevention and control of abnormal water gush in the 1303 working face of Dananhu No.1 mine.

       

    /