麻家梁矿采动双硬顶板工作面覆岩运移规律

吴博文, 张宏伟, 神文龙, 王晶晶

吴博文, 张宏伟, 神文龙, 王晶晶. 麻家梁矿采动双硬顶板工作面覆岩运移规律[J]. 煤矿安全, 2017, 48(10): 51-54.
引用本文: 吴博文, 张宏伟, 神文龙, 王晶晶. 麻家梁矿采动双硬顶板工作面覆岩运移规律[J]. 煤矿安全, 2017, 48(10): 51-54.
WU Bowen, ZHANG Hongwei, SHEN Wenlong, WANG Jingjing. Overlying Rock Movement Law of Double Hard Roof Working Face in Majialiang Coal Mine[J]. Safety in Coal Mines, 2017, 48(10): 51-54.
Citation: WU Bowen, ZHANG Hongwei, SHEN Wenlong, WANG Jingjing. Overlying Rock Movement Law of Double Hard Roof Working Face in Majialiang Coal Mine[J]. Safety in Coal Mines, 2017, 48(10): 51-54.

麻家梁矿采动双硬顶板工作面覆岩运移规律

Overlying Rock Movement Law of Double Hard Roof Working Face in Majialiang Coal Mine

  • 摘要: 以麻家梁煤矿14201双层坚硬顶板工作面为例,进行相似模拟实验和矿压观测,得到了上位坚硬顶板的初次来压步距为106 m,周期来压步距为50~60 m,下位坚硬顶板的初次来压步距为60 m,周期来压步距为20~25 m,发现双硬顶板破断失稳整体呈现“下位短悬臂梁与上位长砌体梁”结构,垮落方式分为下位坚硬顶板单层垮落和上、下位坚硬顶板的同步垮落2种;下位坚硬顶板垮落形成“小周期来压”;上位坚硬顶板垮落给采场及巷道围岩造成较为剧烈的影响,形成“大周期来压”。
    Abstract: Taking 14201 double-decked hard roof working face in Majialiang Coal Mine as an example, the similar simulation experiment and ground pressure observation are carried out. The first pressure step of the upper hard roof is 106 m, the periodic weighting is 50 m to 60 m, the first pressure step of the lower hard roof is 60 m, the periodic weighting is 20 m to 25 m. It is found that the failure behavior of the double-hard roof is presented as “the lower short cantilever beam and the upper long masonry beam” structure. The failure modes of the whole structure are the lower hard single roof collapse and the upper and lower hard roof collapse. The lower hard roof collapse forms “small periodic weighting”, and the upper hard roof collapse causes severe impact on stope and roadway rock and forms “big periodic weighting.”
  • [1] 于洋.特厚煤层坚硬顶板破断动载特征及巷道围岩控制研究[D].徐州:中国矿业大学,2015.
    [2] 钱鸣高,缪协兴,许家林.岩层控制的关键层理论[M].徐州:中国矿业大学出版社,2003.
    [3] 许家林,鞠金峰.特大采高综采面关键层结构形态及其对矿压显现的影响[J].岩石力学与工程学报,2011,33(8):850-855.
    [4] 朱德仁,钱鸣高,徐林生.坚硬顶板来压控制的探讨[J].煤炭学报,1991,16(2):11-20.
    [5] 于斌,刘长友.坚硬厚层顶板的破断失稳及其控制研究[J].中国矿业大学学报,2013,42(3):342-348.
    [6] 张立武.中厚煤层坚硬顶板工作面矿压显现规律分析[J].煤炭技术,2016,35(9):86-88.
    [7] 刘康,侯会伟,武泉林.坚硬顶板工作面覆岩运动规律数值模拟[J].现代矿业,2015(1):32-33.
    [8] 王俊杰,赵磊磊.凤凰山矿XV1304工作面石灰岩坚硬顶板工作面顶板运动规律研究[J].煤炭工程,2014,46(11):54-56.
    [9] 刘长武,郭永峰,姚精明.采矿相似模拟实验技术的发展与问题[J].中国矿业,2003,12(8):6-8.
    [10] 张羽强,黄庆享,严茂荣.采矿工程材料相似模拟技术的发展与问题[J].煤炭技术,2008,27(1):1-3.