短壁跳采胶结充填围岩运动规律研究

    Research on Movement Law of Surrounding Rock of Short-wall Cemented Filling and Skip Mining

    • 摘要: 针对我国“三下”压煤量大,开采成本高、工序复杂等问题,以某矿建筑物下压覆9#煤层为工程背景,提出短壁跳采胶结充填开采方法,并对煤柱和充填体协同作用机理及围岩运动规律进行了研究。主要结论如下:工作面支巷设计宽度为5 m,长度为90 m,全厚开采;步骤一采留比1∶3,顶板变形最大14.1 mm,呈波浪形分布,底鼓不明显;步骤二采留比1∶1,顶板位移量最大30.9 mm,底鼓量2.3 mm;步骤三全采全充,顶板位移呈凹陷形分布,最大位移109.1 mm,底鼓最大10.3 mm;开采过程中煤柱应力呈阶梯状分布,呈波浪形向深部转移,充填体应力阶梯状跳跃增大;短壁全采全充后上覆岩层以弯曲下沉为主,直接顶没有发生明显的冒落;底板破坏呈现 W-波浪型,矿压破坏带为0~2.2 m,煤柱两侧塑性区1.0 m。

       

      Abstract: For the problem of “three unders” mining with high cost and complex process, based on a mine under building covering 9# coal seam, short wall cemented filling and skip mining was proposed. We study synergy mechanism and movement laws of surrounding rock about coal pillar filling body by this mining method. The main conclusions are as follows: the design width of support roadway length and advancing length of working face are respectively 5 m and 90 m in full thickness mining; firstly, the ratio of mining and pillar being 1∶3, the maximum deformation of roof is 14.1 mm, in a wavy distribution, and the bottom deformation is not obvious; secondly, the ratio being 1∶1, the maximum deformation of roof and floor is 30.9 mm, 2.3 mm respectively; thirdly, full mining and full backfilling, the roof displacement is concave shape and the maximum deformation of roof and floor is 109.1 mm, 10.3 mm respectively; in the mining process, stress distribution of coal pillars is staged and gradually transferred to deep. Backfilling stress presents step-shape increase skip; overburden are mainly bent down after full mining and full backfilling, and the direct roof has no obvious caving process. Destructive floor renders W-wavy distribution with 0 to 2.2 m failing zone and the plastic zone on both sides of the coal pillar is located at 1.0 m.

       

    /

    返回文章
    返回