TBM工法在煤矿斜井施工中安全防范重点及应对措施
Safety Protection Emphasis and Countermeasures of TBM Method in Inclined Shaft Construction of Coal Mine
-
摘要: 以单护盾TBM工法在补连塔煤矿2号辅运平硐的工程实践为例,分析说明TBM施工期间安全防范重点及应对措施,为探索TBM技术在煤矿斜井和井下巷道施工的可行性、安全性和可靠性,提供工程实例的借鉴和经验积累。Abstract: Taking the engineering practice of single shield TBM method in 2# auxiliary transported adit of Bulianta Coal Mine as an example, the paper analyzes and introduces safety protection emphasis and countermeasures during the TBM construction, which provides reference and experience of engineering project by exploring the feasibility, safety and reliability of TBM technology in inclined and coal mine underground roadway construction.