万利一矿矿井水复用“零排放”工程实践

    Project Practice of Mine Water Reuse and "Zero Release" in Wanli No.1 Coal Mine

    • 摘要: 为实现矿井水复用“零排放”工程,对万利一矿地下矿井水循环系统进行了规划设计,然而,在按照原规划实施过程中,存在安全隐患且无法满足矿井水处理及复用要求,因此,必须对原工程规划进行新的改进设计。按新规划将42301采空区、42113采空区和42103~42108采空区连为整体储水区施工后,通过注水试验及水质检验证实了其优越性。

       

      Abstract: In order to realize the mine water reuse and "zero release" project, Wanli No.1 Coal Mine made the planning and design of its underground mine water circulation system. However, according to the original plan, there were safety risks and it could not meet the requirements of mine wastewater treatment and reuse in implementation process. Therefore, the original project planning needs to revise. 42301 goaf, 42113 goaf and 42103~42108 goaf were as a whole storage area in the new plan construction. Superiorities of the new plan were proved by water injection tests and water quality inspection.

       

    /