显德汪矿-200 m水平泵房硐室群全断面支护技术
Full Section Supporting Technology for -200 m Level Pump Chamber Group in Xiandewang Mine
-
摘要: 为了解决显德汪矿-200 m泵房硐室群大面积变形破坏的难题,首先通过现场调研初步分析了变形破坏的原因,其次对硐室开挖扰动的应力场进行了区域划分,按应力集中程度的大小由表及里依次形成应力卸载圈、强应力集中圈、次强应力集中圈和应力稳定圈。在此基础上提出了双壳加固理论,由深浅支护体形成的支护壳共同作用,使巷道处于稳定状态。最后结合-200 m水平泵房硐室群的实际情况,设计采用了以锚杆索配合深、浅注浆作为双壳支护的主体,同时辅以底角锚索束+反底拱的全断面联合支护维修方案,取得了较好的控制效果。Abstract: In order to solve problem of large deformation and failure in -200 m Level pump chamber group of Xiandewang Coal Mine, the deformation reason is analyzed by site survey. Besides, the stress field disturbed by chamber excavation is divided into stress unloading circle, strong stress concentration circle, less strong concentration circle and stress stability circle from the outside to the inside according to stress concentration degree. On this basis, the theory of double shell reinforcement is proposed. The support shell formed by the shallow and deep support body ensures the chamber stability. At last, combined with the practical situation of -200 m Level pump chamber group, the support scheme of bolt (anchor) combined with the grouting and angle anchor beam and inverted arch is designed. The field application shows that this support scheme achieves good control effect.
-
-
[1] 王其州,谢文兵,荆升国,等.构造复杂区硐室群围岩失稳机理及控制技术研究[J].采矿与安全工程学报,2014,31(2):263-269. [2] 何满潮,李国峰,任爱武,等.深部软岩巷道立体交叉硐室群稳定性分析[J].中国矿业大学学报,2008,37(2):167-170. [3] 丁国峰,王波,马海涛,等.下石节矿高应力泵房硐室围岩控制技术[J].煤矿安全,2014,45(5):66-69. [4] 李来源,林惠立,魏夕合.深部硐室围岩破坏原因与稳定性控制技术[J].矿业安全与环保,2011,38(6):25-27,30. [5] 李向革,赵卫民,张朝武.保安煤矿采区变电所硐室变形破坏分析及二次注浆加固技术[J].煤矿安全,2013,44(1):86-89. [6] 钱鸣高,刘昕成.矿山压力及其控制[M].北京:煤炭工业出版社,1991. [7] 洛锋.高地应力巷道围岩破坏特征及支护机理试验研究[D].邯郸:河北工程大学,2012.
计量
- 文章访问数: 368
- HTML全文浏览量: 0
- PDF下载量: 0