大采高长工作面过陷落柱回采工艺
Mining Technology of Passing Collapse Column at Large Mining Height and Extended Mining Face
-
摘要: 针对成庄矿5310大采高工作面开采受陷落柱影响的问题,对陷落柱进行了详细的勘探,明确了陷落柱的位置、范围,制定详细的探放水技术措施,对陷落柱进行超前探放水,并制定了过陷落柱的可行性方法。通过控制采高,采用采煤机直接割矸和震动爆破的方式,运用浅截深回采工艺,直接通过陷落柱。结果表明:通过运用直接过陷落柱的方案,减少了工作面搬家工作量,节约了费用,保证了工作面的连续推进,提高了煤炭资源回收率。Abstract: Aiming at the problem that mining at 5310 large mining height working face of Chengzhuang Coal Mine is seriously effected by collapse column with a detailed exploration, we clear the position and range of collapse column, find out the collapse column without water, we propose the feasible method for passing collapse column in large mining height working face. We pass collapse column by controlling the mining height, using shearer to directly cut gangue and vibration blasting, and the mining technology of shallow-frustum. The results show that the scheme for passing collapse column reduces moving workload, saves the cost, extends mining face continuous propulsion, improves the recovery rate of coal resources.
-
-
[1] 孟鑫,王安顺.综采工作面过陷落柱技术初探[J].煤炭技术,2010,29(11):239-240. [2] 张育恒.综放工作面过陷落柱开采技术探讨[J].煤矿开采,2012,17(4):24-26. [3] 李晋平,肖亚宁,万世文.综放工作面遇陷落柱高效开采技术[J].煤炭科学技术,2006,34(10):36-38. [4] 郑学亮.综放工作面过断层技术管理实践[J].煤矿开采,2006,11(6):55-56,79. [5] 冯立松,王耀光.综采放顶煤工作面过陷落柱实践[J].能源技术与管理,2009(2):55-56. [6] 陈昆木.厚煤层大采高回采工艺探讨[J].煤炭技术,2008,27(10):161-162. [7] 王中亮,秦帅,何青源.综放工作面快速过上松下硬陷落柱开采技术[J].煤矿开采,2013(3):81-84. [8] 孟辉,马守君,樊海艳.陷落柱影响采场围岩破坏的数值模拟分析[J].山东科技大学学报,2011,30(5):26-29. [9] 杨为民,司海宝,吴文金.岩溶陷落柱导水类型及其突水风险预测[J].煤炭工程,2005(8):60-63.
计量
- 文章访问数: 403
- HTML全文浏览量: 0
- PDF下载量: 0