顶板瓦斯高抽巷优化布置数值模拟

    Numerical Simulation of Optimal Layout of Roof Gas High-level Drainage Roadway

    • 摘要: 根据采空区上覆岩层移动规律及瓦斯运移规律,结合潞安集团五阳矿7801综放面现场实际,采用FLAC3D数值模拟的手段,对高抽巷顶底板相对移近量、两帮相对移近量,最大主应力进行了分析,明确了采动影响下高抽巷的变形破坏规律,优化了高抽巷的空间布置。

       

      Abstract: According to the laws of overlying strata movement above gob and gas migration, combined the scene of Lu'an Group Wuyang Mine 7801 fully mechanized caving face, by using FLAC3D to analyze the relative displacement between the roof and floor, the relative displacement between the left side and right side, the maximum stress, the laws of deformation and failure of high-level drainage roadway was determined under the mining influence, then the position of high-level drainage roadway was optimized.

       

    /

    返回文章
    返回