Abstract:
The effect factors in the process of kilometer deep hole ground pre-grouting construction were analyzed in consideration of the diversity and complexity of stopping slurry construction by utilizing the method of factor analysis. Three public factors including geological factor (F
1), grouting parameters influencing factor (F
2) and stopping slurry targets factor (F
3) on behalf of the success rate in stopping slurry construction were extracted. As a case, the analysis of ground pre-grouting construction in Xinhu Coal Mine was carried out for Bozhou Coal, in which the feasibility of the proposed method was verified by utilizing the method of Factor Analysis.