麦垛山矿6#煤上行开采可行性分析
Feasibility Analysis on Upward Mining of 6# Coal Seam in Maiduoshan Coal Mine
-
摘要: 为保证矿井安全投产,针对麦垛山矿主采2#煤上部存在的强含水层问题,采用理论计算分析确定2#煤开采后导水裂隙带高度均大于30 m,直接开采将会威胁矿井安全;而通过对下部6#煤的导水裂隙带高度计算可知,6#煤开采后不会造成矿井突水,仅在断层附近对上部煤层存在局部破坏,数值实验直观表明,先采6#煤不会破坏上部煤层,上行开采是可行的。Abstract: In order to ensure mine safety production, according to the problem of existing strong aquifer above 2# main coal seam, theoretical calculation and analysis are applied to determine the height of water flowing fractured zone which are all greater than 30 me after mining 2# coal, direct mining will threaten the safety of coal mine. While the height calculation of water flowing fractured zone shows that 6# coal mining will not cause mine water inrush, there is only partial destruction to upper coal seam near the faults. Numerical experiment intuitively shows that 6# coal mining will not destroy the upper coal seam. Upward mining is feasible.
-
Keywords:
- upward mining /
- water flowing fractured zone /
- numerical experiment /
- aguifer /
- water outburst
-
-
[1] 刘天泉.用垮落法上行开采的可能性[J].煤炭学报,1981(1):18-28. [2] 钱鸣高,石平五.矿山压力与岩层控制[M].徐州:中国矿业大学出版社,2003. [3] 马立强,汪理全,乔京利,等.平四矿近距煤层上行开采研究[J].采矿与安全工程学报,2008,25(3):357-360. [4] 冯国瑞.煤矿残采区上行开采基础理论与实践[M].北京:煤炭工业出版社,2010. [5] 刘传安,张勇,王祖发,等.赵各庄矿深埋厚煤层群上行开采数值模拟研究[J].煤炭工程,2012(3):77.
计量
- 文章访问数: 518
- HTML全文浏览量: 0
- PDF下载量: 1