极薄煤层覆岩连续缓沉运动及其控制

    Continuous Slow Sinking and Its Control of Extremely Thin Seam Overburden

    • 摘要: 对小于0.8 m极薄煤层的覆岩运动形式及机理进行深入研究,提出了1种极薄煤层覆岩运动形式-连续缓沉破坏运动。将连续运动覆岩简化为弹性基础连续板力学模型,推导出工作面前后的顶板挠度曲线z1z2及压力p1p2计算表达式,通过现场观察及运用数值模拟技术,判定达竹煤电集团斌郎煤矿覆岩为连续缓沉运动形式,并提出了相应的支护控制措施,在N1014工作面进行了成功实践。

       

      Abstract: The article studies overburden rock movement form in extremely thin seam which is less than 0.8 m, puts forward movement form of extremely thin seam overburden, continuous slow sinking, which simplifies continuous movement overburden as mechanical model of elastic foundation continuous plate. The paper also deduces the calculated formula of roof deflection curves z1, z2 and pressure p1, p2. Using numerical simulation and investigation, the study determines the movement of Binlang Coal Mine in Dazhu Coal and Electricity Group is continuous slow sinking, and puts forward appropriate control measures.

       

    /